The Chamera Concrete Gravity Dam is across the river Ravi and is part the Chamera Hydroelectric Project. Concrete placement was accomplished by cable crane and tower cranes.
Principal Quantities of Work | ||
Crest Length | 255 M | |
Height | 140 M | |
Chilled Chilled Concrete to be Placed | About 1.4 million cum | |
Excavation | ||
Common | 1,245,345 Cubic meters | |
Rock | 481,067 cubic meters | |
Abutment excavation | 232,843 cubic meters | |
Fill in coffer dams | 515,627 cubic meters | |
Shotcrete | 14,724 Ton | |
Drilling concrete | 27,900 M | |
Chilled Concrete | 1,378,864 cubic meters | |
Form work | 237,068 square meters | |
Chilled Concrete in intake structure and diversion tunnel lining | 23,372 cubic meters | |
Reinforcements | 14,807 MT | |
Anchor bolts and other metal works | 1,055 MT |