(Rs.
in crores)
S.No. |
Name of the Project |
Face value of work completed upto
31.12.2003 |
Total value of work completed upto
31.12.2003 including escalation and extra items |
Estimated value of balance work including
escalation and extra items |
Estimated Completion date |
(1) |
(2) |
(3) |
(4) |
(5) |
(6) |
1 |
Sardar Sarovar (Narmada)
Project, Gujarat |
|
|
|
|
a)
Construction of Concrete Dam |
362 |
869 |
260 |
June, 2006 |
b)
Construction of Underground River
Bed Power House and appurtenant Works
|
86 |
208 |
35 |
October, 2004 |
|
|
|
|
|
|
2 |
Indira Sagar (Narmada) Project, Madhya Pradesh
|
|
|
|
|
a)
Construction of Concrete Gravity Dam
|
240 |
309 |
51 |
June, 2005 |
b)
Construction of Power House |
208 |
291 |
20 |
January, 2005 |
|
|
|
|
|
|
3 |
Tehri
Hydroelectric Project, Uttaranchal |
|
|
|
|
a)
Rockfill Dam and Associated Works |
776 |
1,047 |
257 |
December, 2005 |
b)
Chute & Shaft Spillways |
432 |
565 |
279 |
December, 2005 |
|
|
|
|
|
|
4 |
Dulhasti Hydroelectric Project,Jammu & Kashmir
|
|
|
|
|
a)
Civil Works of Up-stream Area work |
391 |
554 |
120 |
September, 2004 |
b)
Civil works of Down-Stream Area work |
166 |
258 |
49 |
September, 2004 |
|
|
|
|
|
|
5 |
All Civil, Hydromechanical and Balance of Plant works of 400 MW Vishnuprayag Hydroelectric Project, Uttaranchal
|
468 |
468 |
365 |
June, 2006 |
|
|
|
|
|
|
6 |
Tala
Hydroelectric Project, Bhutan |
|
|
|
|
a)
Construction of Head Race Tunnel (RD 6000m to RD 11,130m) from Padechu
Adit
|
113 |
137 |
61 |
December, 2004 |
b)
Construction of Power House and Tail Race Works
|
213 |
357 |
239 |
March, 2006 |
|
|
|
|
|
|
7 |
All Civil and Hydromechanical works of 450 MW Baglihar Hydroelectric Project (Stage-I), Jammu & Kashmir
|
796 |
977 |
1,433 |
December, 2006 |
|
|
|
|
|
|
8 |
All Civil and Hydromechanical works of
300 MW Chamera (Stage–II) Hydroelectric
Project, Himachal Pradesh
|
921 |
1,016 |
35 |
May, 2004 |