JAIPRAKASH INDUSTRIES LIMITED

WORKS IN HAND AS ON 31.12.2003

 

                                                                                                                                                                          (Rs. in crores)

 

 

S.No.

 

 

Name of the Project

Face value of work completed upto 31.12.2003

Total value of work completed upto 31.12.2003 including escalation and extra items

Estimated value of balance work including escalation and extra items

Estimated Completion date

(1)

(2)

(3)

(4)

(5)

(6)

           
9

Teesta (Stage – V) Hydroelectric Project,

Sikkim

 

       

a) Construction of Coffer Dams, Concrete

     Dam, Intake, Desilting Chamber and part

     Head Race Tunnel

 

158

186

 

252

November, 2005

b) Construction of Power House,

     Surge Shaft, Pressure Shafts and

     part  Head Race Tunnel

 

 98

103

 

115

 

September, 2005
           
10

All Civil and Hydromechanical works

of 450 MW Baglihar Hydroelectric

Project (Stage – II), Jammu & Kashmir

 

NIL

 

NIL

 

824

 

50 months from

effective date of start (work likely to start in April, 2004)

 

           
11

All Civil and Hydromechanical works of

520 MW Omkareshwar Hydroelectric

Project, Madhya Pradesh

 

7

7

924

 

October, 2007
           
12

All Civil, Hydromechanical and

Electromechanical works of 1000 MW

Karcham Wangtoo Hydroelectric Project,

Himachal Pradesh

 

NIL

 

NIL

4,179

 

72 months from

effective date of start (work likely to start in April, 2004)

 

 

Total

5,435

7,332

9,498

 